The job sheet
This example shows a document that the The job, written down once magik would produce. The lab does not exist yet: Mojo builds it the moment you click, with your hours, your prices and your tone. What you read below was invented for this page.
The job sheetThe job sheet
Job ST-2611 - 14 rue des Peupliers, Bourg
Drinking water service extension, 22 m trench along the pavement, even-numbered side.
| ItemItem | ValueValue |
|---|---|
| Declared footprint | 22 m x 1.5 m, pavement and verge |
| Maximum depth | 1.40 m |
| Method | 3T excavator, hand digging within 1.50 m of any located line |
| Planned start | Monday 24th, 7:30am |
| Duration | 3 days |
What this sheet fixes and what stops being negotiable after it
The footprint above is the one that goes into the notices. If the route moves by more than two metres on site, it is no longer the same job as far as the notice is concerned: you re-file, you do not widen the line by hand.
Open point
The connection at the property boundary has not been settled with the client. Until it is, the 1.40 m depth stays an assumption and the marking cannot be treated as final.