SPECAvant de Creuser : ta DICT, ton marquage-piquetage et ton constat, chantier par chantier › The job, written down onceExample

The job sheet

Job ST-2611 - 14 rue des Peupliers, Bourg

Drinking water service extension, 22 m trench along the pavement, even-numbered side.

ItemValue
Declared footprint22 m x 1.5 m, pavement and verge
Maximum depth1.40 m
Method3T excavator, hand digging within 1.50 m of any located line
Planned startMonday 24th, 7:30am
Duration3 days

What this sheet fixes and what stops being negotiable after it

The footprint above is the one that goes into the notices. If the route moves by more than two metres on site, it is no longer the same job as far as the notice is concerned: you re-file, you do not widen the line by hand.

Open point

The connection at the property boundary has not been settled with the client. Until it is, the 1.40 m depth stays an assumption and the marking cannot be treated as final.

This lab can be yours, with your data where this example stands.

Mojo builds it during the customize session. Groundworks and utility contractors who file their own dig notices: that is who this one is for.

The job sheet · example · Avant de Creuser : ta DICT, ton marquage-piquetage et ton constat, chantier par chantier | Taquet