The ground marking record
This example shows a document that the The marking record magik would produce. The lab does not exist yet: Mojo builds it the moment you click, with your hours, your prices and your tone. What you read below was invented for this page.
The ground marking recordThe ground marking record
Ground marking record - job ST-2611
Done on 22 August, 9:10am, dry weather. Footprint sprayed over the full 22 m length.
What was traced
| NetworkNetwork | ColourColour | Traced positionTraced position | Gap against planGap against plan |
|---|---|---|---|
| Medium-voltage power | red | centreline 0.80 m from the gutter | matches |
| Gas | yellow | centreline 1.35 m from the gutter | matches |
| Telecom | green | centreline 2.10 m from the gutter | 40 cm out |
The gap, and what we do about it
The telecom duct is traced 40 cm further from the kerb than the plan we received shows. The gap is recorded, photographed and reported to the operator today. It does not block the start: the network is not sensitive and digging will go manual as we approach it.
Had the gap been on gas or power, the call would have been the opposite: stop work and call the operator back, because the position found on site would no longer match the marking.
Upkeep
Marking to be re-checked at the start of each day. Three days of work announced, rain forecast for Wednesday.